在史蒂文站的增加

作为我们1.2亿英镑的东海岸升级的一部分,我们在史蒂文上建造了额外的轨道和平台,以实现更频繁和可靠的服务运行。

这款126米长的平台,连同建造2公里的专用新轨道,信令和架空线路设备,使火车从赫特福德北线(称为赫特福德循环)终止并返回伦敦,而不会在繁忙的情况下占用容量东海岸主要线。

This improves resilience and reliability on the East Coast Main Line and enables a more frequent service to run between Hertford North and Stevenage, giving passengers on the loop better connections with fast mainline services stopping at Stevenage.

工作开始于2019年初,涉及削减斜坡,要求去除71,000吨土壤,安装新的轨道排水和修改宽阔的桥梁和六个山丘桥梁。

Despite restrictions put in place for COVID-19, this £40million project was delivered over a year earlier than planned and was officially opened on Monday 3 August 2020 by the Rail Minister Chris Heaton-Harris.

The new platform includes a passenger lift and stairs to an extended station footbridge, along with two waiting rooms, three sets of seating, a help point and ticket machine and upgraded traincrew facilities.