We are installing a new signalling system in the Clacton-on-Sea area to replace the Victorian equipment with modern technology, bringing it into the 21stcentury.

新的基于计算机的信号将取代使用机械杠杆和套头衫来改变信号和轨道点,以允许列车在轨道之间切换的系统。新系统将由Colchester的电源信号箱控制。

Alterations will also be made to the overhead line equipment and the track layout will be remodelled and updated to cater for a modern railway with powered switches and crossing controlled by the new signals.

Benefits of the programme

These works are a vital part of our strategy to provide a safer, reliable and more efficient railway putting our passengers first. The work will:

  • Improve the overall safety and reliability, reducing faults which cause delays
  • 利用现代技术支持更可持续和高效的铁路
  • Help reduce ongoing maintenance as the new mechanical equipment will be more reliable meaning we can reduce costs and it will be less disruptive to the railway in the future.

£37m investment– Signalling, Track, Civils, Overhead Lines, Power Systems and Telecoms

500m新建轨道– as part of the new track layout to achieve greater reliability and minimise disruption

12 Renewed Signals–现代固态联锁系统
LED Signals

12 Renewed Points– Power operated and linked to the new Signalling system

11 New OLE Structures– and OLE infrastructure alterations in line with new layout

2 New Power systems–用于信号和点加热设备

Modernised Signalling System– To renew the obsolete signalling assets

科尔切斯特驱动信号箱– New train dispatch system controlled from Colchester

新的signallingsystem will compliment Greater Anglia’s new fleet of trains and delivery a better, overall journey experience for passengers.

When are we going to deliver this work?

The early preparation works began in the winter of 2019 and progressed throughout 2020 with major works required throughout winter/spring 2021.

我们将从Saturday 20 February 2021toSunday 14 March 2021and over selected weekends.

Across weekends in September and October 2020, our teams successfully completed the preparatory works ahead of the intensive works in February and March. We’ve now installed 13 new OLE structures, 2 new Relocatable equipment buildings, a new power supply, 6 new signal foundations and over 6000m of new cables.

这项工作是否会影响列车服务?

Mid-week during the intensive works there will be Monday to Friday rail replacement bus service between Clacton and Frinton. Trains will run between Walton and London.

将提供铁路替代巴士服务,以便乘客在以下时间/地点完成旅程:

Between Marks Tey and Clacton-on-Sea and Walton-on-the-Naze:

  • Saturday 13 – Sunday 14 February 2021

在科尔切斯特镇和克拉克顿之间,在纳粹岛上的沃尔顿之间:

  • Saturday 20 February 2021
  • Saturday 27 February 2021
  • Saturday 06 March 2021
  • 2021年3月13日星期六

Between Colchester and Clacton-on-Sea and Walton-on-the-Naze:

  • Sunday 21 February 2021
  • Sunday 28 February 2021
  • 2021年3月7日星期日
  • Sunday 14 March 2021
  • Saturday 20 March – Sunday 21 March 2021
  • 2021年4月18日星期六17日-周日
  • Saturday 24 – Sunday 25 April 2021

Between Frinton-on-Sea and Clacton-on-Sea:

  • Monday 22 – Friday 26 February 2021
  • 周一1 - 2021年3月5日星期五
  • Monday 8 – Friday 12 March 2021

联系我们about our renewals programme

If you’re interested in finding out more about our programme to replace signalling equipment, please contact us by visiting our contact us page or by calling our 24-hour national helpline on 03457 11 41 41.